A standard electrical panel replacement usually takes an electrician 4 to 8 hours, so most homes have power back the same day.
- Simple swap: Same size and location, about 4 to 6 hours.
- Service upgrade: Moving from 100 to 200 amps with a new meter base and service wires, often a full day.
- Relocation or extra work: Moving the panel, adding grounding or fixing old wiring can take 2 or 3 days.
- Before and after: Permits, utility disconnect and reconnect, and the city inspection can add days of scheduling.
Plan for the power to be off for most of the work. Keep fridges closed, charge phones and ask your electrician to confirm the utility appointment before work day.